এই টান্সফরমারটি রেডি করলাম বুয়েট টেষ্ট করার জন্য!
Tech Team Engineering Ltd
250KVA Dyn11
ONAN

BUET Test list.

1. Resistance measurement of all windings.
2. Ratio test.
3. Polarity and phase test.
4. No-load losses at rated voltage & rated frequency.
5. Excitation current at rated voltage & rated frequency.
6. Impedance voltage & load measurement.
7. Induced potential test ( low frequency)
8. Dielectric test of oil.
9. Impulse & temperature rise tests.
10. Short circuit tests.
11. Open circuit tests.
12. Rated capacity KVA.